The renovation QC checklist to run before you sign off

Most defects in Sarawak homes are not bad workmanship — they are checks nobody ran at the right stage. This is the staged QC checklist ELS uses: what we verify before production, during install, on wet-area and M&E points, and at handover. Use it to hold any contractor accountable, or let ELS run its checks at the hold-points your commissioned scope includes.

Start Pre-CheckSee how ELS worksWhatsApp ELS
Who this checklist is for
Homeowners about to approve production drawingsAnyone managing a renovation across multiple tradesBuyers comparing contractor quotes who want a QC standardWet-kitchen, bathroom and flood-prone home projects
Quick decision rules

How to use this checklist

QC is about catching problems at the cheapest stage to fix them — on paper, not after install.

IfThen
A check was skipped when its work was doneStop and resolve it now — a fix on paper costs a fraction of a fix after fabrication
A cabinet sits in a wet zone (wet-kitchen base, vanity, laundry)Confirm the carcass is ACP or honeycomb aluminium — not just 'moisture-resistant' board
A board is labelled E0 / E1 / ENFTreat that as emission grade only — it says nothing about waterproofing
A check fails during installLog it with a photo and stop that trade before they build over it
You are running this yourself without a coordinatorInsist on one approved scope all trades sign to — undocumented changes are where disputes start
Check group A · stages 3–4

Before production / drawing approval

The cheapest stage to fix anything. Every check here is a line on paper, not a saw cut.

Dimensions match the site, not the floor planDeveloper plans are routinely off by centimetres; an unverified drawing produces a cabinet that won't fit.
Material specified per moisture zoneDry runs can use moisture-resistant board; for damp positions the actual water exposure and the approved specification decide, and direct-water positions keep ACP or honeycomb aluminium. This must be fixed on the drawing.
Appliance and sink models confirmed before drawingHob cut-outs, oven housings and sink reveals are model-specific; a late swap means a rebuilt carcass.
Socket, switch and water-point positions overlaidM&E points must be plotted against the cabinet drawing so nothing lands behind a fixed panel.
Door swing, drawer clash and walkway clearance checkedTwo drawers or a door and an appliance that collide are obvious on paper and expensive after install.
One approved scope all trades sign toA single locked scope is what lets you hold tiler, electrician and cabinet maker to the same plan.
Check group B · stage 8

During production & install

Catch it while the trade is still on site — not after the next trade builds over the problem.

Carcass material matches the approved specVerify the board or aluminium delivered is the grade specified — substitutions happen quietly.
Edge banding sealed on all cut edgesIn Sarawak humidity, an unsealed edge is the first place a board swells and delaminates.
Carcass level, plumb and securely anchoredOut-of-level runs throw off doors, worktops and the whole alignment downstream.
Hinges, runners and hardware are the agreed brandHardware is the first thing to fail; a cheaper substitute won't survive daily use in a humid kitchen.
Wall fixings suit the actual wall typeHollow block, brick and partition walls each need the right anchor or a loaded wall cabinet pulls out.
Check group C · stages 6–7

Wet-area & M&E checks

Where Sarawak homes fail soonest: moisture, water connections and electrical points.

Wet-zone carcasses are ACP or honeycomb aluminium, or protected P6 under a kitchen sink with ALUMAX's listed protections where ALUMAX's site measurement finds P6 suitableMoisture-resistant board is not waterproof; unprotected board under a wet-kitchen sink will eventually fail. Protected P6 is allowed there only with ALUMAX's listed protections and where ALUMAX's site measurement finds P6 suitable.
Plumbing pressure-tested before boxing inA slow leak behind a panel is invisible until the carcass below is already rotting.
Sealant lines continuous at sink, hob and backsplashGaps in sealant are the direct path for water into the carcass and adjacent walls.
Wet-area floor falls toward the drainStanding water from a flat or reverse fall is a daily moisture load on every cabinet base.
Electrical points earthed and clear of water zonesSockets near a sink without correct earthing and spacing are a safety and code problem.
Flood-prone homes have a raised or sacrificial base detailIn flood zones the base detail decides whether one flood ruins the whole run.
Check group D · stage 10

Snagging & handover

The final walk where you confirm everything works, aligns and is documented before you pay the balance.

Every door and drawer aligned and soft-closingUneven gaps and slamming doors signal hardware that wasn't adjusted at handover.
Surfaces free of scratches, dents and glue marksCosmetic defects are far harder to claim once the balance is paid and trades have left.
All appliances and water points tested liveA hob, tap or extractor should be run on site, not assumed to work.
Silicone, caulk and trims cleanly finishedMessy sealing is both a look problem and the most common spot for early water ingress.
Defects logged with photos and a fix dateA written snag list with dates is your leverage; verbal promises rarely get honoured.
Warranty, care notes and material list handed overYou should leave knowing what was installed and how to maintain it in this climate.

The hold-point ladder

Ten hold points, in the order the work reaches them. Each says what is checked, what evidence is recorded, which role signs, and what may proceed or must wait. Where no approved text defines a signatory or a failure response, the rung says so.

The ceiling closes only after the concealed services have been inspected and the wet-area test has been accepted. The order of ceiling, tiling and flooring is agreed for each project. This is a dependency sequence, not a rigid calendar. See the ten-stage work sequence

The QC sheet behind it lists 23 checks in four check groups. See the QC sheet specimen

  1. Stage 3 · Coordinated technical design

    1

    Design sign-off

    Checked
    Layout, render, M&E overlay and finish schedule all approved.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note; A signed sign-off sheet
    Signs
    Client, ELSRoles ELS expects to sign at this point
    Proceed
    Cleared: releases ordering
    Stop
    Not cleared: ordering waits
    If it fails
    Not yet stated
  2. Stage 5 · Site preparation

    2

    Demolition scope

    Checked
    Correct walls and finishes removed; structure intact.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases wet works
    Stop
    Not cleared: wet works waits
    If it fails
    Not yet stated
  3. Stage 6 · First fix and substrates

    4

    M&E first-fix positions

    Checked
    Every socket, switch, light, water-point and AC point matches the drawing before plaster hides them.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases plastering
    Stop
    Not cleared: plastering waits
    If it fails
    Not yet stated
  4. Stage 7 · Waterproofing and finishes

    3

    Waterproofing test

    Checked
    Flood / pressure test holds before anything covers the membrane; falls to gully.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases tiling / screed
    Stop
    Not cleared: tiling / screed waits
    If it fails
    Not yet stated
  5. 5

    Ceiling void

    Checked
    Services (AC, wiring, ducting) correct before the ceiling closes.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note; The ceiling and MEP coordination acceptance form
    Signs
    The specialistRoles ELS expects to sign at this point
    Proceed
    Cleared: releases ceiling close-up
    Stop
    Not cleared: ceiling close-up waits
    Why this point matters
    The specialist signs a ceiling and MEP coordination acceptance form before closing the ceiling. Once closed, repositioning a concealed valve, driver, pipe or AC component becomes recovery work, not a simple ceiling correction. Products subject to Malaysian construction-material controls should also be checked for the applicable conformity documentation.
    If it fails
    Not yet stated
  6. Stage 8 · Fabrication and installation

    6

    Delivery inspection

    Checked
    Right items, correct finish codes, quantities, no transit damage.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases install
    Stop
    Not cleared: install waits
    If it fails
    Not yet stated
  7. 7

    Cabinet interface

    Checked
    Wall / floor level and the M&E points behind the run correct before fixing.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases joinery install
    Stop
    Not cleared: joinery install waits
    If it fails
    Not yet stated
  8. Stage 9 · Second fix and FF&E

    8

    Power-on test

    Checked
    Circuits, appliances and fans commissioned.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases deep clean + defects
    Stop
    Not cleared: deep clean + defects waits
    If it fails
    Not yet stated
  9. 9

    Pre-delivery clean

    Checked
    No wet or dusty trade remains before furniture arrives.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note
    Signs
    Not yet stated
    Proceed
    Cleared: releases loose furniture
    Stop
    Not cleared: loose furniture waits
    If it fails
    Not yet stated
  10. Stage 10 · Commissioning and handover

    10

    Final snagging

    Checked
    Full QC checklist signed; care & warranty pack issued.
    Evidence recorded
    The QC sheet records a passed check with its date, initials and a note; A signed sign-off sheet
    Signs
    Client, ELSRoles ELS expects to sign at this point
    Proceed
    Cleared: releases handover
    Stop
    Not cleared: handover waits
    If it fails
    Not yet stated
What's included

What QC covers — and what it doesn't

A QC walk verifies that approved work was built correctly. It is not a redesign and it cannot fix decisions that were never specified.

A QC walk includes
  • Verifying built work against the approved scope and drawings
  • Checking material grade by moisture zone
  • Wet-area, sealant and M&E point inspection
  • A documented snag list with photos
A QC walk does not
  • Redesign work that was never specified or approved
  • Make 'moisture-resistant' board waterproof after the fact
  • Cover structural, façade, drainage or waterproofing trades unless scoped as a project
  • Replace a written contract or warranty with the contractor
What drives the price

What a QC engagement depends on

ELS runs these checks at the hold-points a coordination engagement includes. These are the factors that shape it.

Number of stages walkedA single handover walk differs from staged QC across drawing, install and wet-area stages.
Trade count and coordination loadMore trades to one scope means more interfaces to verify and align.
Site locationELS site visit: RM150 local (within 30 km of Sibu centre), payable when booked and credited to your order if you go ahead; outstation visits are quoted per job. The best first step is to visit the showroom and book an appointment. For a measure or site visit booked through the showroom, the RM150 fee may be waived, subject to availability.
Wet-area and flood-risk complexityFlood-prone and heavy wet-zone homes need more inspection points and detailing.

Indicative only — the final quotation follows site measurement, material selection and approved scope.

How to prepare

What to have ready for a QC walk

The walk goes faster and catches more when these are on hand.

  • The approved production drawings and final scope
  • The material and hardware specification list
  • Confirmed appliance and sink models
  • M&E layout showing socket, switch and water points
  • Any quote or contract terms covering defects and warranty
  • A phone or camera to photo-log every snag
  • Notes on which areas are wet zones or flood-prone
Where ELS works

Based in Sibu — elsewhere in Sarawak by quotation.

Sibu as standard. Elsewhere in Sarawak by quotation, subject to schedule and capacity. Other towns are by arrangement.

KuchingSamarahanSibuBintuluMiri
Renovation QC in Sarawak

Common questions

What is a renovation QC checklist actually for?

It's a staged set of checks that confirm work is specified and built correctly at each point — before production, during install, on wet-area and M&E details, and at handover. The aim is to catch problems at the stage where they're cheapest to fix, ideally on paper before anything is cut or fabricated.

Can I run this checklist myself?

Yes — it's written so a homeowner can hold a contractor accountable stage by stage. The hard part is having one approved scope that every trade signs to, and knowing the material logic, especially that 'moisture-resistant' board is not waterproof in a wet zone. Where coordination across trades gets heavy, that's the layer ELS runs.

Why does material choice keep coming up in QC?

Because the most common Sarawak defect is the right-looking cabinet built in the wrong material for its moisture zone. We choose by moisture zone, not budget: dry runs can use moisture-resistant board — a substrate rating, which is a separate axis from the E0/E1/ENF emission grade and is still not waterproofing — while wet-kitchen bases, vanities and laundry zones need ACP or honeycomb aluminium. Under a kitchen sink, protected P6 is allowed only with ALUMAX's listed protections and where ALUMAX's site measurement finds P6 suitable.

When in the project should QC start?

Before production. The drawing-approval stage is where a fix costs a fraction of what it costs after fabrication or install. Starting QC only at handover means you're inspecting decisions that were locked in weeks earlier, when changing them is expensive or impossible.

How is ELS different from an interior designer running site visits?

ELS provides commissioned design and specification through ELS Studio. ELS+ delivers only the works in its separate contract. Product-only purchases go to ALUMAX or the appropriate supplier. ALUMAX supplies the products, with installation included or quoted separately according to the product and the agreed scope, as its quotation states; ELS plans scope, specifies materials, lighting and M&E, coordinates the trades' information to one approved scope, recommends the order of the work and checks the hand-offs set in the commissioned scope. The checklist is the operational side of that role.

What does a wet-area check focus on?

Carcass material (ACP or honeycomb aluminium, not unprotected moisture-resistant board; protected P6 under a kitchen sink only with ALUMAX's listed protections and where ALUMAX's site measurement finds P6 suitable), pressure-tested plumbing before anything is boxed in, continuous sealant at sink, hob and backsplash, floor falls toward the drain, and earthed electrical points clear of water. In flood-prone homes we also check the base detail so one flood doesn't ruin the whole run.

What should I bring to the QC walk?

The approved drawings and final scope, the material and hardware spec list, confirmed appliance and sink models, the M&E layout, any contract terms on defects and warranty, and a camera to photo-log every snag. Note which areas are wet zones or flood-prone so those get the right level of scrutiny.

Does QC replace a warranty or contract?

No. QC verifies that approved work was built correctly and produces a documented snag list — that's leverage, not a legal substitute. You still want a written contract and warranty with each party that supplies or installs. The QC record makes those documents far easier to enforce.

References

External references for the standards and climate data cited above. ELS is not affiliated with these organisations.

Prepared by George Wong — Founder, ELSFormer senior research engineer, Fortune 500 · Based in Sibu, Sarawak

The recommended build order and its QC hold-points

Keep planning with ELS

Related ELS services

Not sure which service fits? Start the free Pre-Check. Already know your scope? Enquire directly

Not sure which you need? Start with the free Pre-Check: it suggests which service to ask about.

Start Pre-Check
Free · No obligation

Run this QC standard on your project with a free Renovation Pre-Check